Monday, May 18, 2015

In-place Grinding of Asphalt, Mobilization, and Sewer Televising Anticipated this Week.

Work Completed Last Week:
·         Resident Preconstruction meeting on Tuesday, May 12th.

Work Anticipated This Week:
·         In-place grinding of roadway on Monday, May 18th
·         Televising of existing sanitary sewer and storm sewer lines.
·         Mobilization of equipment

The contractor is anticipating to begin underground utility construction on Tuesday, May 26th, following the Memorial Day weekend.  

Friday, May 8, 2015

Resident Informational Meeting Scheduled for May 12th at 6:30 PM

Resident pre-construction informational meeting scheduled for Tuesday, May 12th at 6:30 to be held at the Village of Glenview, Police Department Community Room, 2500 East Lake Avenue.

We look forward to meeting with you and discussing the project.