Friday, August 28, 2015

Concrete Curb & Gutter This Week

Work Completed Last Week:
·         Removal and replacement of storm manhole at Ferndale and Sherwood.
·         Roadway excavation and grading
·         Excavation and installation of aggregate base for concrete curb & gutter 

Work Anticipated This Week:
·         Monday – Install string line in preparation for concrete curb & gutter
·         Tuesday – Grading and necessary adjustments in preparation for concrete curb & gutter
·         Wednesday – Pour concrete curb & gutter
·         Thursday – Complete pouring concrete curb & gutter, grading behind curb & gutter, and grading for driveway restoration.
·         Friday – Continue with grading behind curb & gutter, grading for driveway restoration, and possibly begin asphalt and concrete driveway restoration (depending on work progress). 

The next 10 days or so will have the greatest inconvenience regarding driveway access. Please have all vehicles removed from your driveways and garages by 7:00 AM on Monday, August 31st. We anticipate driveway access will be stored by Wednesday September 9th depending on work progress and weather conditions. This will allow the concrete ample time to cure as well grading of the existing roadway and paving the first 2 layers of asphalt pavement prior to driveway access being restored.

We understand the inconvenience that is caused due to driveway access being restricted, especially over the Labor Day weekend. We thank you in advance for your patience and understanding as this phase of construction takes place.

Monday, August 24, 2015

Underground Utility Work Completed. Roadway Reconstruction Beginning

Work Completed Last Week:
·         Completed storm sewer catch basin and inlet installations
·         Completed storm sewer service installations
·         Removed and abandoned existing water main facilities
·         Removed and abandoned existing storm sewer piping and structures.
·         Removed existing concrete curb & gutter
·         Removed existing driveways
·         Layout / staking for roadway improvements
·         All underground utility construction is completed.

Work Anticipated This Week:
·         Removal and replacement of storm sewer manhole at Ferndale and Sherwood
·         Roadway excavation and aggregate base course installation along Heatherfield Lane.

This week the roadway excavation will begin along Heatherfield Lane. During this process, access to your driveways may be restricted during working hours, but will be restored each evening. The contractor will knock on your door to have you move any vehicles out of your driveway or garage prior to restricting your access.

The week of August 31st will have the greatest inconvenience regarding driveway access. Based on the current schedule, starting Monday, August 31st at 7:00 AM through Thursday, September 10th, driveway access will be restricted due to concrete curb & gutter installation and asphalt paving. We understand these driveway restrictions will be in affect over the Labor Day Weekend and everything possible will be done to reduce the amount of time you are out of your driveway. Additional notification, including parking instructions, will be provided in the near future.

The Village has also been in contact with the school district regarding parking regulations, parking needs, and traffic flow due to the construction operations coinciding with the start of the school year.

Thank you again for all your patience and understanding during these construction operations.

Monday, August 17, 2015

Storm Sewer Nearly Completed. Roadway Improvements to Begin

Work Completed Last Week:
·         Continued with installation of catch basins and inlets
·         Continued with storm sewer service installations.
·         Completed storm sewer main line installation at intersection of Heatherfield and Beech Drive.

Work Anticipated This Week:
·         Complete storm sewer catch basin and inlet installations
·         Complete storm sewer service installations.
·         Removal and abandonment of existing water main facilities and storm sewer piping
·         Removal of existing concrete curb & gutter
·         Removal of existing driveways, all driveways will have aggregate installed after they are removed to restore access
·         Layout/staking for roadway improvements.
·         General site clean-up

The underground utility improvements are nearly completed and should be completed by the middle of this week. Once the underground construction is completed, the project will be transitioning to the roadway improvements phase of construction. The roadway excavation will begin this week with the removal of existing concrete curb & gutter and driveways.

The week of July 24th the roadway excavation will continue with removal of the existing asphalt pavement. We are anticipating the concrete curb & gutter installation will begin the week of August 31st. During this time, residents will not have access to their driveways. The current schedule indicates residents will be without driveway access from August 31st to September 10th to allow for concrete curb & gutter and asphalt paving operations. Residents will be notified regarding exact dates and parking options as the schedule is confirmed.

We understand there are significant inconveniences associated with the roadway reconstruction process and restrictions to driveways. Please be ensure everything possible is being done to limit the amount of time driveway access is restricted. Thank you in advance for your patience and understanding during these construction operations.

Monday, August 10, 2015

Underground Utility Construction Anticipated to be Completed by End of Week

Work Completed Last Week:
·         Completed storm sewer main line installation along Heatherfield Lane.
·         Continued with installation of catch basins and inlets
·         Continued with storm sewer service installations.

Work Anticipated This Week:
·         Complete storm sewer catch basin and inlet installations
·         Complete storm sewer service installations.

 We anticipate the underground utility construction (storm sewer, sanitary sewer, and water main) will be completed near the end of this week. Once the underground utility construction is completed, the project will transition to the roadway reconstruction phase. Residents will continue to be informed as the roadway reconstruction process gets closer and restrictions to driveway access.