Monday, September 28, 2015

Sod Restoration Completed. Sewer Lining and Final Paving Scheduled for This Week.

Work Completed Last Week:
·         Fine grading of landscaped areas
·         Topsoil installation
·         Sod installation
·         General site clean-up 

Work Anticipated This Week:
·         Continue with general site clean-up
·         Internal lining of existing sanitary sewers
·         Perform final walk-through to create a list of items to be remedied.
·         Paving final lift of asphalt pavement.

Thank you again for your patience and understanding has you have been living in a construction zone for the past several months. Now that the curb & gutter, asphalt pavement, and sod installation is completed, the project is nearing completion. We hope that you are happy with the end result.

Monday, September 21, 2015


Work Completed Last Week:

·         Adjust manholes in new pavement.

·         Begin parkway restoration and topsoil installation.

·         Complete minor clean up and work to new manholes and water system.

 
Work Anticipated This Week:

·         Begin parkway restoration and topsoil installation.

Friday, September 11, 2015


Work Completed Last Week:

·         Fine grading of aggregate base course.
·         Remove and replace poor base materials.
·         Pave first layer of asphalt pavement.
·         Continue backfilling behind curbs.
·         Continue asphalt driveway restoration.

 

Work Anticipated This Week:

·         Complete asphalt driveway restoration.
·         Adjust manholes in the new pavement.
·         Begin parkway restoration and topsoil installation.

Thank you all for your patience during this portion of construction which has restricted your driveway access.  Driveway access is no longer permanently restricted, however there may be some minor restrictions (10-20 minutes) during remaining work.

Monday, September 7, 2015

First 2 Layers of Asphalt Pavement Scheduled This Week

Work Completed Last Week:
·         Poured Concrete Curb & Gutter
·         Restored Concrete Driveways
·         Backfilled behind new curb & gutter
·         Excavated for asphalt driveway restorations
·         Install first layer of asphalt for driveway restorations. 

Work Anticipated This Week:
·         No work Labor Day Weekend.
·         Fine grading of aggregate base course
·         Remove and replace poor base materials.
·         Pave first 2 layers of asphalt pavement.
·         Continue backfilling behind curbs
·         Continue HMA driveway restorations.

Thank you again for all your patience and understanding while access to your driveways is restricted. We understand what a significant inconvenience this causes to your daily lives and are doing everything possible to get the work completed in a timely manner. Depending on work progress and weather conditions, all driveway access should be restored by the end of next week.

Thanks again for all your patience and understanding.

Have a safe and enjoyable Labor Day Weekend.