Monday, October 19, 2015

Project Completed

All on-site work along Heatherfield Lane and within the easement along Rio Vista is now completed.

We would like to take this opportunity to thank all the residents that lived within those roadways and the surrounding area for your patience and understanding for the past several months when you have lived through the construction project. We understand what significant inconveniences are caused when you live around these construction projects and do everything possible to make the projects go as smoothly as possible. Our hope is that you are satisfied with the end result of the project.

In the next few weeks, the Village will be sending out a resident survey regarding the project. Please take the time to fill out this survey, the Village uses these comments to make improvements for other project moving forward throughout the Village.

This will also be the last blog update for the project. We hope you found the posts informative and useful.

Monday, October 12, 2015

Rio Vista Storm Sewer Completed

Work Completed Last Week:
·         General site clean-up.
·         Internal lining of existing sanitary sewer along Beech Drive

Rio Vista Storm Sewer
·         Completed storm sewer installation
·         Asphalt driveway restoration.

Work Anticipated This Week:
·         No work scheduled on-site.

Rio Vista Storm Sewer
·         Landscape restoration.

Monday, October 5, 2015

Final Asphalt Paving Completed. Rio Vista Storm Sewer On-Going.

Work Completed Last Week:
·         Final layer of asphalt pavement
·         Internal lining of existing sanitary sewers
·         Final walk-through to note any repairs needed along project site
·         General site clean-up.
Rio Vista Storm Sewer
·         Installed new storm sewer from river to Rio Vista Road
·         Directional drilled storm sewer under existing tree
·         Connected existing sump pump connections to new storm sewer 

Work Anticipated This Week:
·         General site clean-up
·         Internal lining of sanitary sewers along Beech Drive
Rio Vista Storm Sewer
·         Remove and preparatory work for asphalt driveway replacement
·         Landscape restoration.

The project is nearly completed now that the final asphalt surface has been installed. Thank you again for all your patience and understanding has you have lived in a construction area over the past few months. Hopefully you are satisfied with the end project.