Monday, October 19, 2015

Project Completed

All on-site work along Heatherfield Lane and within the easement along Rio Vista is now completed.

We would like to take this opportunity to thank all the residents that lived within those roadways and the surrounding area for your patience and understanding for the past several months when you have lived through the construction project. We understand what significant inconveniences are caused when you live around these construction projects and do everything possible to make the projects go as smoothly as possible. Our hope is that you are satisfied with the end result of the project.

In the next few weeks, the Village will be sending out a resident survey regarding the project. Please take the time to fill out this survey, the Village uses these comments to make improvements for other project moving forward throughout the Village.

This will also be the last blog update for the project. We hope you found the posts informative and useful.

Monday, October 12, 2015

Rio Vista Storm Sewer Completed

Work Completed Last Week:
·         General site clean-up.
·         Internal lining of existing sanitary sewer along Beech Drive

Rio Vista Storm Sewer
·         Completed storm sewer installation
·         Asphalt driveway restoration.

Work Anticipated This Week:
·         No work scheduled on-site.

Rio Vista Storm Sewer
·         Landscape restoration.

Monday, October 5, 2015

Final Asphalt Paving Completed. Rio Vista Storm Sewer On-Going.

Work Completed Last Week:
·         Final layer of asphalt pavement
·         Internal lining of existing sanitary sewers
·         Final walk-through to note any repairs needed along project site
·         General site clean-up.
Rio Vista Storm Sewer
·         Installed new storm sewer from river to Rio Vista Road
·         Directional drilled storm sewer under existing tree
·         Connected existing sump pump connections to new storm sewer 

Work Anticipated This Week:
·         General site clean-up
·         Internal lining of sanitary sewers along Beech Drive
Rio Vista Storm Sewer
·         Remove and preparatory work for asphalt driveway replacement
·         Landscape restoration.

The project is nearly completed now that the final asphalt surface has been installed. Thank you again for all your patience and understanding has you have lived in a construction area over the past few months. Hopefully you are satisfied with the end project.

Monday, September 28, 2015

Sod Restoration Completed. Sewer Lining and Final Paving Scheduled for This Week.

Work Completed Last Week:
·         Fine grading of landscaped areas
·         Topsoil installation
·         Sod installation
·         General site clean-up 

Work Anticipated This Week:
·         Continue with general site clean-up
·         Internal lining of existing sanitary sewers
·         Perform final walk-through to create a list of items to be remedied.
·         Paving final lift of asphalt pavement.

Thank you again for your patience and understanding has you have been living in a construction zone for the past several months. Now that the curb & gutter, asphalt pavement, and sod installation is completed, the project is nearing completion. We hope that you are happy with the end result.

Monday, September 21, 2015


Work Completed Last Week:

·         Adjust manholes in new pavement.

·         Begin parkway restoration and topsoil installation.

·         Complete minor clean up and work to new manholes and water system.

 
Work Anticipated This Week:

·         Begin parkway restoration and topsoil installation.

Friday, September 11, 2015


Work Completed Last Week:

·         Fine grading of aggregate base course.
·         Remove and replace poor base materials.
·         Pave first layer of asphalt pavement.
·         Continue backfilling behind curbs.
·         Continue asphalt driveway restoration.

 

Work Anticipated This Week:

·         Complete asphalt driveway restoration.
·         Adjust manholes in the new pavement.
·         Begin parkway restoration and topsoil installation.

Thank you all for your patience during this portion of construction which has restricted your driveway access.  Driveway access is no longer permanently restricted, however there may be some minor restrictions (10-20 minutes) during remaining work.

Monday, September 7, 2015

First 2 Layers of Asphalt Pavement Scheduled This Week

Work Completed Last Week:
·         Poured Concrete Curb & Gutter
·         Restored Concrete Driveways
·         Backfilled behind new curb & gutter
·         Excavated for asphalt driveway restorations
·         Install first layer of asphalt for driveway restorations. 

Work Anticipated This Week:
·         No work Labor Day Weekend.
·         Fine grading of aggregate base course
·         Remove and replace poor base materials.
·         Pave first 2 layers of asphalt pavement.
·         Continue backfilling behind curbs
·         Continue HMA driveway restorations.

Thank you again for all your patience and understanding while access to your driveways is restricted. We understand what a significant inconvenience this causes to your daily lives and are doing everything possible to get the work completed in a timely manner. Depending on work progress and weather conditions, all driveway access should be restored by the end of next week.

Thanks again for all your patience and understanding.

Have a safe and enjoyable Labor Day Weekend.