Water main improvements at intersection of
Ferndale Road and Heatherfield Lane.
·
Completed required testing of newly installed
water main along Heatherfield Lane. Water main can now be placed into service.
·
Nicor Gas completed gas main and service
replacement between Beech Drive and Fernadale Road. If you have any concerns
regarding your gas service, please contact Nicor Gas.
·
General site clean-up
Work Anticipated This Week:
·
Storm sewer installation at the intersection of
Ferndale Road and Heatherfield Lane.
Thank you in advance for dealing the traffic delays and inconvenience
associated with the closure of the Heatherfield Lane and Ferndale Road
intersection. Your patience and understanding is greatly appreciated.