Storm sewer installation at intersection of
Ferndale Road and Heatherfield Lane
·
Storm sewer installation along Heatherfield Lane
from Ferndale Road to Beech Drive
·
Water service replacement along Heatherfield
Lane starting at Ferndale Road and working north towards Sherwood Road.
Work Anticipated This Week:
·
Water service replacements along Heatherfield
Lane continuing to work north towards Sherwood Road.
New water services are being installed from the new water
main to the existing b-box within the Village right-of-way. New services will not
be installed all the way to your home. During water service installation, water
to individual homes will be turned off while the transition is made. Typically
the water is turned off for 1-hour. The contractor will knock on the door of
each home prior to turning off the water. It is difficult to determine the
exact timing of the water shut-off; therefore, 24-hour notice is not given. The
contractor will work with you to determine the best time to shut-off the water
to the greatest extent possible.
Thank you for all your patience and understanding on Monday
while the intersection of Ferndale Road and Heatherfield Lane was closed to
accommodate the construction of the large diameter storm sewer in the area.
There is additional work to be performed within the intersection, but we are
not anticipating it will require the entire intersection to be closed for an
extended period of time.
We also appreciate the understanding of those residents that
were without water on Monday to accommodate the storm sewer construction at the
intersection of Ferndale Road and Heatherfield Lane.