Monday, May 18, 2015

In-place Grinding of Asphalt, Mobilization, and Sewer Televising Anticipated this Week.

Work Completed Last Week:
·         Resident Preconstruction meeting on Tuesday, May 12th.

Work Anticipated This Week:
·         In-place grinding of roadway on Monday, May 18th
·         Televising of existing sanitary sewer and storm sewer lines.
·         Mobilization of equipment

The contractor is anticipating to begin underground utility construction on Tuesday, May 26th, following the Memorial Day weekend.