Monday, June 1, 2015

Sanitary Sewer Repairs to Begin This Week

Work Completed Last Week:
·         In-place grinding of the roadway
·         Preconstruction televising of sewers
·         Tree trimming
·         Mobilization of equipment and materials.

Work Anticipated This Week:
·         Begin sanitary sewer service replacements

We apologize for the delay in start of construction. It was anticipated the work was going to begin a week early than anticipated, but due to unforeseen circumstances, the work was delayed a week later than anticipated.