Monday, September 28, 2015

Sod Restoration Completed. Sewer Lining and Final Paving Scheduled for This Week.

Work Completed Last Week:
·         Fine grading of landscaped areas
·         Topsoil installation
·         Sod installation
·         General site clean-up 

Work Anticipated This Week:
·         Continue with general site clean-up
·         Internal lining of existing sanitary sewers
·         Perform final walk-through to create a list of items to be remedied.
·         Paving final lift of asphalt pavement.

Thank you again for your patience and understanding has you have been living in a construction zone for the past several months. Now that the curb & gutter, asphalt pavement, and sod installation is completed, the project is nearing completion. We hope that you are happy with the end result.