Monday, July 27, 2015

Water Main and Service Replacement Completed

Work Completed Last Week:
·         Completed water service replacements along Heatherfield Lane.
·         Made connections between existing water main and newly installed water main at:
o   Heatherfield Lane and Sherwood Road
o   Heatherfield Lane and Beech Drive
o   Heatherfield Lane and Ferndale Road
·         Installed storm sewer catch basins and inlets at the intersection of Ferndale Road and Heatherfield Lane.
·         Water main and service replacements are completed.

Work Anticipated This Week:
·         Continue with storm sewer installation along Heatherfield Lane.
·         Begin storm sewer service replacements along Heatherfield Lane.
·         Abandon old fire hydrants and valves.

Now that the water main and service replacements are completed, we do not anticipate any more water main shut downs. Thank you for your patience and understanding during the various water main shut downs over the past few weeks, either scheduled or due to emergency repairs.