Work Completed Last Week:
·         Water main improvements at intersection of Ferndale Road and Heatherfield Lane.
·         Completed required testing of newly installed water main along Heatherfield Lane. Water main can now be placed into service.
·         Nicor Gas completed gas main and service replacement between Beech Drive and Fernadale Road. If you have any concerns regarding your gas service, please contact Nicor Gas.
·         General site clean-up

Work Anticipated This Week:
·         Storm sewer installation at the intersection of Ferndale Road and Heatherfield Lane.

 Due to the storm sewer improvements scheduled next week, the intersection of Heatherfield Lane and Ferndale Road will be closed 7/6/15 through 7/10/15 during construction hours only, 7am-5pm – (weather delays could shift closure dates). If weather delays occur, additional notification will be provided. The intersection will be open to traffic before and after construction hours each day.

Thank you in advance for dealing the traffic delays and inconvenience associated with the closure of the Heatherfield Lane and Ferndale Road intersection. Your patience and understanding is greatly appreciated.