Friday, July 10, 2015

Water Service Replacements On-Going

Work Completed Last Week:
·         Storm sewer installation at intersection of Ferndale Road and Heatherfield Lane
·         Storm sewer installation along Heatherfield Lane from Ferndale Road to Beech Drive
·         Water service replacement along Heatherfield Lane starting at Ferndale Road and working north towards Sherwood Road.

Work Anticipated This Week:
·         Water service replacements along Heatherfield Lane continuing to work north towards Sherwood Road.

New water services are being installed from the new water main to the existing b-box within the Village right-of-way. New services will not be installed all the way to your home. During water service installation, water to individual homes will be turned off while the transition is made. Typically the water is turned off for 1-hour. The contractor will knock on the door of each home prior to turning off the water. It is difficult to determine the exact timing of the water shut-off; therefore, 24-hour notice is not given. The contractor will work with you to determine the best time to shut-off the water to the greatest extent possible.

Thank you for all your patience and understanding on Monday while the intersection of Ferndale Road and Heatherfield Lane was closed to accommodate the construction of the large diameter storm sewer in the area. There is additional work to be performed within the intersection, but we are not anticipating it will require the entire intersection to be closed for an extended period of time.

We also appreciate the understanding of those residents that were without water on Monday to accommodate the storm sewer construction at the intersection of Ferndale Road and Heatherfield Lane.