Water Main Almost Completed. Required Testing Started.

Work Completed Last Week:
·         Water main installation along Heatherfield Lane
·         Begin required testing of newly installed water main.
·         Nicor Gas on-site replacing gas main and services along Heatherfield Lane from Beech Drive to Ferndale Road

Work Anticipated This Week:
·         Perform necessary testing of newly installed water main
·         Water main installation along Heatherfield Lane at Ferndale Road
·         Nicor Gas to complete the gas main and service replacement between Beech Drive and Ferndale Road