Friday, June 12, 2015

Sanitary Sewer Improvements Completed. Water Main to Begin

Work Completed Last Week:
·         Remaining sanitary sewer improvements. All sanitary work is now completed.
·         Performed needed tree removal.

Work Anticipated This Week:
·         Preparatory work in anticipation for beginning water main installation.
·         Water main installation along Heatherfield starting at Ferndale and working north towards Sherwood

Thank you to those residents that were affected by the scheduled water main shut down in order to complete the final sanitary sewer manhole replacement on Friday.

As the water main replacement begins, there will be instances when the water will need to be shut-down to perform connections between the existing and new systems. These shut-downs typically last between 4 and 6 hours. Residents will be notified 24-hours in advance prior to any scheduled water main shut-down. Currently a water main shut down for the southern half of Heatherfield on Tuesday, June 16th.

Thanks again for all your patience and understanding as the construction continues.